Wednesday, 28 September 2011

moving paint pots

I firstly got started by looking at the job sheet to find out what job I was going to be doing.
I then starting filling out a risk assessment on the task.

After completing the risk assessment I started by checking the delivery ticket and made any changes that were needed.
I then started putting on my P.P.E

Boots- to protect my feet from dropping paint
Gloves- to protect my skin from the paint
Goggles- to protect my eyes

after putting on all P.P.E i started to check the route to make sure that there were no obstructions.
After making sure the route was clear I started moving the paint from the storeroom into the workshop
"moved 2 at a time"
I moved the paint until the room was empty then I moved them all back in the same order I took them out
after completing the task i cleaned up the area and reported back to the site manager.


moving loost ballast/sand

first I checked the job sheet to find out what needed to be done.

next I started by filling out the risk assessment on the task and the partner that was helping move 1 ton of sand.
after completing the risk assessment i started by looking at the delivery ticket and making changes to the order.
 I then started putting on my P.P.E
Boots- to protect my feet from the wheelbarrow
Gloves- to protect my hands/skin from the sand
Goggles- from the sand/ dust from my eye

I then got a shovel and a wheelbarrow and started moving the ballast/sand with the other collegues untill the bag was empty then refilling it back up.
after finishing this task i reported back to my site manager.

moving bag's of ballast

first i checked the job sheet to find out what i was about to do "moving bags of ballast"
after checking the job sheet i started filling out a risk assessment on the task

i then checked the delivery ticket and made some changes on the ticket
after that i checking the delivery ticket i checked the route that i was going to take
"outside college to the workshop and back outside"

i then put on my P.P.E
Boots to protect my feet from the ballast falling on my feet
Gloves to protect my skin
Goggles to protect any ballast/dust going into my eye

after putting on my ppe i started picking up a pallet and placed it in the workshop for the ballast to be stacked on,
i then started moving ballast 1 at a time by putting it on my shoulder until all the ballast was moved to the workshop and back again.

after i finished the task i cleaned up the area where i was working then i reported back to the site manage for my next job.

Monday, 26 September 2011

plasterboard task

firstly I looked at the job sheet from the site manager to see what task has to be done.
after I carried out a risk assessment on each other and the task
I next checked the delivery ticket for the order, after making some changes
I then began to check the route that I was going to take to make sure there was no obstructions


I then began putting on my P.P.E
Boots- to protect my feet from falling objects
Glasses- to protect from dust from the plasterboard's.
gloves- to protect my skin from the plasteboard's.

I then began moving the plasterboard " 2 people per board "
from the workshop to a empty workshop then moving them back.
stacked on top of each other so they dont bow or bend out of shape.
after i finished moving the plasterboards i reported back to the site manager.

cement block task

first we selected a partner to complete the job sheet and looked at what task we was about to do.
we then carried out a risk assessment on each other and the task.
after the risk assessment,  I checked the delivery ticket for the order "quantity and product"
after I made some changes on the order i signed thge delivery ticket.

i then checked the route that we would take for any obstructions "cars and other workers"
i then began putting on my P.P.E.

"Boots" - to protected my foot from any falling items that may be dropped
"Gloves"- to protected my skin from sharp edges "e.g cuts"
"Glasses" - to protect from dust on the blocks

I then began by pushing the wheel barrow to the desination "place of the blocks"
I then started loading the wheel barrow up with cement blocks " 4-6 blocks at a time"
and began pushing them up the hill watching for oncoming obstructions.

after completing the task I cleaned up the area and reported to the site manager

Tuesday, 13 September 2011

Starting multi trade construction

first we look at the job sheet that was given at the start of the day, then carried out a risk assessment on my colleague "Lloyd" then one on the task.
after finishing the assessment i checked the delivery ticket for quantity and product, then after making some changes "facing bricks - common house bricks" and the number from 150 to 60.

I then started to make sure the route is clear of obstructions i then put on my PPE and put down a wooden prop to put the bricks on. I carried around 6 bricks at a time, stacked in a jenga style till i had 60 bricks on the wooden prop.

last of all i cleaned the area and reported to the site manager. =)